Sample Questions
Q) Which of the following characteristics of the conflict and the conflict management process should be recognized by the managers of the project, while managing conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.
a) Conflict resolution should focus on issues, not personalities.
b) The conflict a search for alternatives is natural and strength.
c) The opening to resolve the conflict.
d) Conflict is an individual problem.
Q) That formula is used if the project had a blood-alcohol level of $ 450,000 you spent $ 191,000, and you have 40 full percent although it is supposed to be 55 percent done and management wants to know performance index of times your project?
a) ($ 450,000 - $ 180,000) / ($ 450,000 - $ 191,000)
b) $ 450,000 - $ 477,500
c) $ 180,000 / $ 247,500
d) $ 180,000 - $ 247,500
Q) A company hires a programmer for one of his projects. What skills should have efficiently owning the work with the project team? Each correct answer represents a complete solution. Choose three.
a) the monitoring of performance
b) the run schedule
c) Command
d) feasibility planning
Q) Which of the following is not one of the power control planning process?
a) Organizational Process Assets
b) Change requests
c) the project's termination request
d) Project document updates
Q) You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $ 345,000 to complete. If the project is completed ahead of schedule, the organization will receive a $ 5,000 bonus per day for early completion. Management has asked you to develop an aggressive program to create as many bonuses as possible, but you must be careful not to increase the risk of the project beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase the risk of the project?
a) By using the critical chain method
b) Crashing
c) Adding leads to project work
d) fast tracking
Who this course is for:
- Those who want to get knowledge on Certification & Check your Skill Test while attend this Practice Test
Instructor
Top Hatrix Hub is an information center that provides effective information on all of this. Certification Practice Test and Video Training from a variety of Technologies.Top Hatrix Hub companies is dedicated to helping you learn in an easy and stand-in manner. It is an information center interested in learning and leading the world of IT certifications.
If you want to develop strong knowledge and good scores on every practice test and course, contact us!