Lesson Overview: Welcome to How to Run a Risk Workshop.
Join the community: https://44riskpm.community/communities/groups/44pm-training-community/home?invite=68dd7ad4c65dc4f63b7269c1
Join the email list: https://forty-four-pm.kit.com/7a75bbd62d
Welcome to the beginning of your journey toward becoming a confident, capable risk workshop facilitator.
This course is designed for:
- Project managers in both Agile and traditional environments
- PMP® and PMI-RMP® candidates looking to deepen their risk management skills
- Team leads, analysts, or engineers stepping into project risk leadership roles
This lesson sets the foundation by giving you an orientation to the program structure, essential resources, and tips to make the most of your learning experience.
What You’ll Learn in This Course:
? How to prepare and facilitate a risk workshop with confidence
? How to apply workshop strategies to real-world projects
? Tools, templates, and facilitation frameworks used in both certification prep and on-the-job execution
? How to confidently run a session whether you’re facing a sprint team or a multi-million-dollar initiative
Tips to Maximize Your Progress
- Watch at 1.5x speed – Save time while still absorbing the material
- Lower video quality if internet is slow – Avoid buffering and stay focused
- Engage, apply, repeat – This course works best when you take consistent action in your projects
Final Thought: Learning to Lead Through Discomfort
Running a risk workshop isn’t about perfection — it’s about preparation, leadership, and decision support. You don’t need to be fearless, just willing to step forward and grow through the discomfort.
I built this course to be simple, actionable, and real. If you put in the work, you’ll come out the other side with a skillset most project managers only wish they had.
Have Fun in the Course!
-Russ
Downloads for This Lesson
Be sure to downloads all the resources for this course.
These tools are designed to help you immediately implement what you learn, whether you’re studying for a certification or applying this in the field.
Lesson Overview: The Power of the Risk Workshop
This lesson kicks off your journey by framing why the risk workshop matters — and why so many project managers get it wrong.
Most treat risk workshops like another meeting.
But this course is here to show you how to run a true workshop that drives risk identification, builds ownership, and supports proactive decision-making.
Whether you’re:
A seasoned project manager looking to level up
A risk analyst wanting better outcomes
A team leader improving stakeholder collaboration
Or someone studying for the PMI-RMP or PMP®
You’re in the right place.
This course is built on real-world practice, not just theory. And it’s designed to deliver immediate value for your career.
Key Takeaways from This Module
Here’s what you’ll walk away with after this lesson:
Clarity on the course mission – To give you practical, reusable, and reliable skills to lead risk workshops
An understanding of who benefits – From new PMs to PMO leaders, this course meets you where you are
Access to the 44Risk PM Risk Workshop toolkit – Templates, checklists, and scripts designed to make facilitation easier
A success mindset – Reps and real-world use matter more than memorization
This isn’t a sit-back-and-watch course. It’s a hands-on playbook for leading smarter projects through risk leadership.
Pro Tips for Applying What You Learn
Practice beats theory – Treat this course like a gym. The more you apply what you learn, the stronger your facilitation skills become.
Take notes – Capture insights, personal reflections, and risk ideas as you go.
Use, reflect, revise – Don’t just use the tools — adapt them to your team and stakeholder needs after testing.
Connect with Russ – Use the comments, join the community, or reach out on LinkedIn. You’ve got support.
Next Step
Click “Mark Complete” to move on to the official course introduction, where we’ll explore the framework, phases, and flow of a successful risk workshop.
Remember: This course only works if you do. Let’s get started.
Lesson Overview: Why the Risk Workshop Matters
This lesson begins your shift from “project meeting manager” to “risk workshop facilitator.”
Too many project managers make the mistake of running risk workshops like they’re just another recurring sync — slide decks, status updates, and shallow conversations.
But a risk workshop is not just a meeting.
It’s a focused, collaborative session designed to:
Identify and assess real project threats and opportunities
Create shared ownership for addressing risks
Build alignment across teams and stakeholders
Lay the groundwork for better decisions, faster action, and fewer surprises
In other words, it’s one of the most strategic sessions a project leader can run.
Key Takeaways from This Module
By the end of this lesson, you’ll be able to:
Explain the difference between a meeting and a workshop
Understand why skipping or mishandling the workshop stage leads to invisible risks and avoidable failures
Recognize how a well-run workshop improves stakeholder communication, trust, and follow-through
Set the tone for proactive, not reactive project risk management
Reflect and Engage
Ask yourself:
Have I ever run a risk workshop that actually surfaced meaningful risks?
Did my last “risk meeting” lead to real decisions or just notes?
Who was responsible for what — and did they follow through?
Next Step
Click “Mark Complete” to move forward to the next module!
Let’s start running risk workshops that matter.
Lesson 1.1 Overview: Foundations of Risk Workshops
This lesson lays the foundation for your understanding of why risk workshops are critical to project success — and how they differ from typical meetings.
You’ll learn:
Why most project risks aren’t technical — they’re invisible issues caused by misalignment, missed signals, or poor planning
The four levels of uncertainty every project manager must understand
When to run a risk workshop (hint: it’s more often than you think)
Why risk workshops are about team alignment and proactive leadership, not just checklists
How opportunity-focused discussions can boost project performance
This isn’t just about dodging threats — it’s about discovering potential.
Key Concepts Introduced
Most Projects Don’t Fail on Scope or Budget — They Fail on Surprise
The best risk managers aren’t clairvoyants — they’re facilitators who create the space for unknown knowns and blind spots to surface. And that starts with a real risk workshop, not just a slide deck and a call.
Risk Workshops Build Shared Understanding
Unlike a weekly status meeting, a risk workshop is:
Structured for participation
Focused on surfacing and analyzing uncertainty
Designed to build trust, ownership, and communication
You’ll develop these facilitation muscles throughout this course — and you’ll leave knowing how to turn one-off workshops into a team habit.
The Hidden Power of Opportunity
Risk management isn’t just about avoiding disaster — it’s also how you find unexpected wins.
Well-run risk workshops allow you to:
Save money by identifying process improvements
Deliver early by removing blockers
Increase stakeholder confidence through alignment
Don’t ignore positive risk. Capture it.
Who Should Call for a Risk Workshop?
The Project Manager often leads it
But any team member, stakeholder, or sponsor can raise the flag
Risk awareness is everyone’s job — and a healthy team culture encourages it
Up Next
Click “Mark Complete” to continue to Lesson 1.2: The Risk Management Plan
Here we’ll dig into the engine behind the workshop — your risk plan.
Lesson 1.2 Overview: The Risk Management Plan
This lesson introduces the risk management plan — your blueprint for effective project risk management and the cornerstone of every great workshop.
You’ll learn:
What a risk management plan is and why it’s critical
Why planning must happen before risk identification
The essential elements that must be in place before your workshop begins
What happens when you skip planning (spoiler: it’s not pretty)
How to use the plan to align your team, prevent chaos, and keep your workshop focused and productive
What Is a Risk Management Plan?
The risk management plan defines how your project will identify, analyze, respond to, and monitor risks.
It answers the who, what, when, and how behind risk management, including:
Risk thresholds and categories
Roles and responsibilities
Methods of risk identification and analysis
Tools and templates to be used
Timing and frequency of risk activities
It’s not just a formality — it’s a requirement for PMI-aligned projects and a necessity for high-performing teams.
Why Planning Comes First
Jumping into a risk workshop without a plan is like showing up to a mission without a map.
Without planning, teams:
Talk past each other
Drift into irrelevant topics
Miss critical risks
Leave the session with incomplete or unusable outputs
But when you start with a clear plan:
Your team comes aligned and prepared
You get structured input, not scattered opinions
You avoid scope creep in your risk discussions
You can focus on execution, not confusion
Remember: Risk management is a discipline — not a guessing game.
Quick Readiness Check
Use this Risk Workshop Readiness Checklist (included in your downloads) and ask yourself:
Have I finalized and shared the risk management plan with the team?
Are the workshop objectives clearly defined?
Have I identified and invited the right mix of participants?
Are all tools, templates, and documents ready to go?
Have I established ground rules and made expectations clear?
If you can answer “yes” to all five, you’re set up for success.
Final Thought
Planning is the first real risk control you’ll ever perform in a project.
A complete, shared risk management plan empowers you to:
Lead workshops with purpose
Avoid wasted time
Build team alignment
Surface and respond to risk earlier than your competition
The best facilitators don’t “wing it.” They walk into the room with the foundation already laid.
Next Step
Click “Mark Complete” to continue to Lesson 1.3: Pre-Workshop Preparation
Here, we’ll walk through the day-zero prep steps to guarantee your workshop starts strong.
Congratulations!
You’ve officially completed Module 1: Foundations of Risk Workshops — and that’s a huge win. The hardest part is often getting started, and you’ve now laid the groundwork for effective, proactive risk management on every project you lead.
What You’ve Learned So Far
Over the past few lessons, you’ve:
Discovered why risk workshops matter and how they help teams avoid costly surprises
Learned the difference between a typical project meeting and a real risk workshop
Explored PMI’s four categories of uncertainty: known knowns, known unknowns, unknown knowns, and unknown unknowns
Understood the importance of timing — when and why to run workshops throughout the project lifecycle
Built a working knowledge of the risk management plan — the blueprint that aligns teams before risk discussions ever begin
You now have the tools and the mindset to approach risk workshops with clarity, structure, and confidence.
Reflection Activity: Commit to Action
Before you move on, complete this quick action step:
Write down one specific action you’ll take before your next risk workshop.
Here are a few ideas to get you started:
“I’ll finalize and circulate a formal risk management plan before kickoff.”
“I’ll create a workshop agenda and send out risk prep materials in advance.”
“I’ll invite a SME who’s never been part of risk discussions before.”
“I’ll review my assumptions log and build a checklist to surface overlooked risks.”
Even small actions can lead to massive improvement when repeated across projects.
What’s Next: Prep for Real-World Execution
In Module 2, we’ll start turning plans into practice.
You’ll learn:
How to choose the right participants
How to draft a risk workshop agenda
What to include in your pre-workshop briefing
How to assemble your tools, templates, and risk data inputs
You’ve built a strong foundation. Now it’s time to put your learning to work and run workshops that actually move the needle on your projects.
Next Step
Click “Mark Complete” to continue to Module 2: Workshop Preparation
You’re doing great. Let’s keep building momentum — the next lesson is where the action begins.
Lesson 2.1 Overview: Inputs & Tools for a Risk Workshop That Works
Every successful risk workshop starts before the meeting begins.
The work you do ahead of time — the documents you bring, the people you prepare, and the tools you set up — determines whether your workshop will be focused and productive or frustrating and ineffective.
In this lesson, you’ll learn:
The essential documents to gather before a workshop
How the Work Breakdown Structure and Risk Breakdown Structure support risk conversations
How to use assumptions and constraints to trigger deeper thinking
Which tools to use to capture and track risk data
Why checklists are underrated but essential
Let’s walk through what you need to have in place before your session starts.
Key Inputs for Risk Workshops
1. Work Breakdown Structure (WBS)
Think of this as your project’s blueprint. The WBS breaks work down into manageable components — making it easier to identify schedule-related risks.
Bring a copy (digital or physical) so team members can reference it during discussions.
2. Risk Breakdown Structure (RBS)
The RBS groups risks by type (technical, external, financial, etc.) and helps avoid tunnel vision.
Use it to prompt your team to think beyond their individual tasks and consider the full project landscape.
3. Assumptions and Constraints
Assumptions are what you believe to be true, even if you’re not 100% sure. Constraints are the hard limits (e.g., budget, time, scope).
These often turn into high-impact risks when they’re wrong or shift unexpectedly.
Use the worksheet to document these in advance — then challenge them during your workshop with “what if” questions.
Other Key Documents to Bring (PMI-Recommended)
Project charter
Requirements documentation
Cost and schedule estimates
Stakeholder register
Lessons learned from previous projects
These documents provide historical and contextual insight — helping your team think critically during the risk workshop.
The Power of Risk Checklists
A risk checklist is a curated list of common risks from previous projects. It’s a memory jogger, a conversation starter, and a training tool all in one.
Review past project checklists
Pull in risks from lessons learned
Use the provided template to guide your session
Checklists help ensure you’re not starting from scratch — and help reduce overlooked risks, especially for newer teams.
Timing Tip: Send Inputs Early
Don’t wait until the workshop starts to distribute these materials.
? Send everything at least 24 hours in advance.
This gives participants time to prepare and allows you to drive engaged conversation — not last-minute confusion.
Action Step
Pick one input or tool from this lesson that you’re not currently using — and commit to integrating it into your next project.
Even one change in your preparation process can dramatically increase the value of your workshop.
Next Up
Click “Mark Complete” to continue to Lesson 2.2: Pre Workshop Prep
We’ll cover how to build your invite list and create an agenda that drives results — not just another meeting.
You’re getting closer to running risk workshops your team will thank you for.
Lesson 2.2 Overview: Pre-Workshop Preparation
Welcome to the lesson that can make or break your risk workshop: the preparation phase.
The most successful risk workshops don’t start at the opening discussion — they begin well before anyone sits at the table.
This lesson is your guide to:
Setting clear objectives and scope
Choosing the right participants
Structuring thoughtful invitations and pre-work
Creating the conditions for a productive, focused, and engaging session
If you want your workshop to deliver real value, the work starts now.
Step 1: Define Clear Objectives and Scope
A risk workshop without a purpose is just another time-waster.
Set a one-sentence objective that’s specific, measurable, and relevant.
Example: “Our goal is to identify and prioritize the top 10 risks that could impact Phase 1 of the system launch.”
Then set the scope boundaries — what’s in, what’s out.
Example: “Risks beyond October will not be discussed during this session.”
? Pro Tip: Share objectives in advance so participants walk in with the right mindset. No surprises = better engagement.
Step 2: Select the Right Participants
The quality of your workshop depends on who’s in the room.
Include:
Project Leader or PM – Facilitates the session
Core Team & SMEs – Understand project tasks and deliverables
Additional Experts – Bring technical or organizational knowledge
Key Stakeholders & Sponsors – Offer authority, resources, and alignment
Potential Risk Owners – Will follow through on assigned risks
Ideal group size?
– Aim for 10–14 people. Large enough for diverse input, small enough for real discussion.
Step 3: Send Strategic Invitations
Avoid generic invites like “Risk Workshop – Conference Room B.”
That’s how you lose attention before the meeting starts.
Instead, send a personalized message that includes:
The workshop’s purpose and scope
The detailed agenda (time blocks and topics)
Access info (location, links, dial-in)
List of prep materials to review
Clear expectations (e.g., “Come prepared to share your top 3 concerns”)
Timing Tip: Send this at least 7 days in advance with a reminder 48 hours before.
Ask participants to reply and confirm — not just for accountability, but to begin the conversation before the session even starts.
Key Takeaways
Pre-workshop prep sets the tone for success
Clear objectives and well-defined scope eliminate confusion
Choosing the right participants = better insights and stronger alignment
Personalized invites build commitment and help you hit the ground running
The best risk workshops feel smooth because they were planned that way
Action Step
Write your draft invite now.
Use the editable template to customize:
Workshop purpose
What you need from participants
What they’ll gain from attending
What to review or bring
Send it to your future self or a colleague for review.
This small prep habit will make your workshops stand out as professional, focused, and effective.
Up Next
Click “Mark Complete” to continue to Lesson 2.3: Structuring the Workshop Day
Next, we’ll build your agenda block-by-block and prepare you to lead a high-impact session.
You’re one step closer to risk workshop mastery.
Lesson 2.3 Overview: Wrapping Up Pre-Workshop Preparation
You’ve done it — you’ve laid the full groundwork for a successful risk workshop.
In this final lesson of Module 2, we’re tying it all together and doing a readiness self-check to confirm you’re equipped, aligned, and ready to lead.
What comes next? Running the session.
But before we get there, let’s lock in the core principles that will make your workshop productive from the first five minutes onward.
Self-Check: Are You Ready?
Ask yourself the following before proceeding:
? Have you confirmed and shared your workshop objectives and scope?
? Is your attendee list complete with the right mix of team members, SMEs, and decision-makers?
? Have you circulated the agenda and project background documents (e.g., charter, WBS, RBS)?
? Did you assign pre-work (e.g., submit top 3 risks) and request responses ahead of time?
? Have you sent reminders and confirmation requests to all participants?
? If you answered yes to all five, you’re ready to lead a workshop that produces real results.
What’s Next: Workshop Facilitation in Action
In the next module, we shift from planning to execution.
You’ll learn:
How to structure your workshop agenda for momentum and clarity
How to open strong and set the right tone
Tips for real-time facilitation, risk capturing, and assigning risk owners
What to do when things go off-track — and how to bring the team back together
It’s time to move from behind-the-scenes prep to real-time leadership.
Next Step
Click “Mark Complete” to move into Module 3: Running the Workshop Day
You’ve built the foundation. Now let’s make the session itself just as powerful.
Lesson 3.1 Overview: Workshop Agenda and Setup
A high-impact risk workshop doesn’t happen by chance — it’s built with purposeful structure, clear time blocks, and ground rules that create space for everyone to contribute.
In this lesson, you’ll learn how to:
Choose the right workshop format (from 1 to 5 days)
Set up a detailed agenda tailored to your project’s complexity
Manage time effectively during the session
Create an environment where your team feels safe, focused, and motivated to participate
Apply facilitation best practices to keep discussions on track
Why Structure Matters
An agenda isn’t just for keeping time — it’s your tool for:
Guiding participation
Avoiding off-topic rabbit holes
Reducing stress
Delivering measurable outcomes
When people know what to expect and when, they show up better prepared, contribute more meaningfully, and stay more engaged.
Agenda Setup Tips
Here’s how to make your agenda actually work:
Set clear time limits for each item and use a visible timer
Create a Parking Lot for off-topic ideas
Assign a rotating timekeeper so the facilitator can focus on guiding discussion
Build in frequent breaks — mental fatigue kills good risk conversations
Document everything — capture ideas, actions, and lessons learned in real time
Download the sample agendas and use the Agenda Builder Worksheet to create your version today.
Establish Ground Rules for Engagement
Setting expectations early prevents conflict later. Here are some essential workshop rules:
Respect every contribution — no judgment during brainstorming
Stay on agenda — focus on the current topic
One speaker at a time — avoid crosstalk
No idea is too small — everything gets captured
Always close with clear next steps and assigned owners
These rules help create a safe and focused environment, especially during risk brainstorming, where participation quality determines success.
Up Next
Click “Mark Complete” to continue to Lesson 3.2: Kicking Off the Workshop
You’ll learn how to open strong, introduce the session effectively, and set the tone for meaningful participation from the very first minute.
Lesson 3.2 Overview: Starting the Workshop Right
The first 30 minutes of your risk workshop are where success is set in motion.
This lesson walks you through how to:
Set the tone for focus, clarity, and collaboration
Facilitate introductions that go deeper than names
Clarify project objectives and scope in plain language
Create a psychologically safe environment
Establish behavioral norms and expectations
Visibly anchor the group to workshop goals and outcomes
If you want high engagement and quality results, it all begins with a well-planned, well-led kickoff.
Facilitated Introductions that Matter
Skip the boring name-around-the-room intros. Use these six kickoff questions to get the team talking and thinking:
What’s your name and role on this project?
What experience do you have with risk management?
What do you hope to get out of today’s workshop?
What’s your biggest concern for this project?
What’s one opportunity you see for success?
What’s one thing you need to be successful in this session?
? Tip: For larger groups (10+), break into small groups for intros to avoid time burn while keeping the engagement high.
Re-State the Objectives and Scope — Out Loud
Don’t assume your team remembers what the project is about or why this session matters.
Take a moment to:
Summarize the project’s purpose
Define what part of the project this workshop covers
Clarify what is not in scope (to prevent derailment)
Remind the team of what success looks like for today’s session
This simple alignment step pays dividends throughout the day.
Use a Process Visual to Frame the Session
Show your team where they are in the risk management journey:
Identification
Assessment
Response
Monitoring
Use a one-page visual to orient everyone — especially useful for sponsors or stakeholders not involved in day-to-day delivery.
Today’s focus: Identification + Initial Assessment
Set Behavioral Expectations
Reinforce these ground rules up front:
One person speaks at a time
All ideas are valid during brainstorming — no judgment
Stay on agenda and respect time blocks
Contribute actively and respectfully
Questions are encouraged — silence is not alignment
Your tone, structure, and openness here shape the entire workshop’s effectiveness.
Reflection: Prepare Your Next Kickoff
Ask yourself:
What part of your past workshop kickoffs went well?
Which intro question would help uncover risks early?
What’s one behavior you want to encourage at your next session?
Next Step
Click “Mark Complete” to move to Lesson 3.3: Module Conclusion
Now that you’ve kicked things off, it’s time to guide the team through identifying risks that matter.
Let’s move from setup to spotting the real issues that will define your project’s success.
Lesson 4.1 Overview: Techniques to Identify Project Risks
You’ve prepared your team and structured your workshop — now it’s time to dig into the core of risk workshops: identifying threats and opportunities.
In this lesson, we cover three essential techniques you’ll use again and again:
Structured Brainstorming
Assumptions & Constraints Analysis
Checklist Review
Each technique is designed to:
Improve participation
Uncover hidden risks
Build team awareness and shared understanding
These tools don’t just improve your risk register — they help you become the kind of leader who prevents surprises and drives clarity.
Technique 1: Structured Brainstorming
Brainstorming is the foundation of most risk workshops. But to be effective, it needs to be structured — not chaotic.
Why It Works:
Captures a wider range of risks by leveraging group experience
Encourages creative thinking and collaboration
Helps identify both threats and opportunities
? Use tools like sticky notes, whiteboards, or digital boards to collect ideas fast.
Bonus Tip: Use the Risk Breakdown Structure (RBS) as a category prompt to cover areas like technical, schedule, external, and financial risks.
Technique 2: Assumptions and Constraints Analysis
Assumptions and constraints often hide high-impact risks. They’re the iceberg beneath the waterline.
Example:
Assumption: Vendor X will deliver on time
Risk: If delayed, the project timeline slips
Constraint: All testing must be in-house
Risk: If internal resources are limited, testing delays occur
How to Apply:
Write out major assumptions and constraints
Ask: “What if this is wrong?” or “What if this changes?”
Identify the resulting risk
Document both in your tracker as a pair
? Use your project charter, WBS, and team conversations as prompts for surfacing assumptions you may be taking for granted.
Technique 3: Checklist Review
Checklists are your fail-safe tool. They help you catch common risks that may otherwise be forgotten.
Use a checklist to:
Prompt memory
Identify risks that didn’t surface during brainstorming
Cross-check past projects and industry standards
Go line by line:
Ask: Could this risk apply to our project?
Mark Yes / No / Maybe
Adjust the checklist to your project’s size, domain, and complexity
? Always combine the checklist with open discussion to encourage context-specific thinking.
Reflection & Application
Take a moment to reflect:
Which of these three techniques have you used before — and which one is new to you?
What risk in your current or recent project may have been missed because it wasn’t surfaced through one of these methods?
What technique are you most excited to try in your next workshop?
? Share your thoughts in the course community or note them in your workbook. The more we reflect, the stronger our facilitation becomes.
Up Next
Click “Mark Complete” to continue to Lesson 4.2: Running the Risk ID Session
You’ve identified the risks — now we’ll learn how to write, refine, and assign them so your risk register becomes a powerful action tool.
You’re doing great. Let’s keep going.
Lesson 4.2 Overview: Facilitating the Risk ID Session
You’ve prepared your inputs and selected your techniques — now it’s time to lead the room.
Risk identification is a team sport. Your role as the facilitator is to create an environment where:
Everyone participates
All ideas are captured
Creative thinking is encouraged
Risks are surfaced that might otherwise be missed
This lesson focuses on how to make your session inclusive, visible, and productive.
Participation is Power: No Passengers Allowed
A quiet room leads to blind spots. Make it your goal to hear from everyone — not just the confident or extroverted.
Strategies to foster engagement:
Directly invite quieter team members to share
Use breakout groups for large workshops
Reinforce psychological safety by reminding participants: all ideas are valid during this phase
Acknowledge and display contributions visibly to show they matter
? When people feel heard, they contribute more — and better.
Think Bigger: Move Beyond the Obvious
Don’t stop at the surface-level threats.
Use these facilitator prompts to stretch team thinking:
“What could go wrong that we haven’t talked about yet?”
“What are we assuming will go right that might not?”
“What is outside our control but could impact the project?”
“Where do dependencies or unknowns create risk?”
Encourage hitchhiking: When one idea sparks another, let the creativity roll.
Balance: Threats and Opportunities
Risk management isn’t just about fear — it’s also about upside potential.
Be intentional about dedicating time to:
“What could go right unexpectedly?”
“Is there a chance this risk could actually open a door for us?”
“What opportunities might we miss if we only focus on problems?”
Examples:
Threat: Vendor is late with delivery
Opportunity: Vendor delivers early — enabling early launch or resource reallocation
? Opportunities are often overlooked — but they can be game changers.
Reflect & Apply
Consider your next workshop and reflect on the following:
What will you do to make sure everyone contributes?
Which risk capture method will work best for your team?
How will you balance threats and opportunities in your discussions?
Next Step
Click “Mark Complete” to continue to Lesson 4.3: Rationalizing and Describing Risks Clearly
We’ll take what you’ve captured and turn it into clear, usable, and actionable risks ready for prioritization and ownership.
You’re building real momentum — let’s keep going.
Lesson 4.3 Overview: Risk Identification Recap & Reflection
Congratulations! You’ve completed Module 4: Risk Identification — the core of running a high-impact, actionable risk workshop.
In this module, you’ve gone beyond theory and into practice. You now know how to:
Facilitate inclusive and structured brainstorming
Surface hidden risks through assumptions and constraints analysis
Use checklists to ensure you never miss the obvious or the repeated
Capture both threats and opportunities with clarity and purpose
Foster a space where teams contribute freely and think creatively
You’re not just managing risks — you’re facilitating smarter decisions.
Action Steps
What’s the #1 technique you’ll apply from this module in your next project?
What would you add to your risk identification process based on what you’ve learned?
? Write your answers in your workbook, or better yet — share them in the comments.
We all benefit when we share how these ideas apply in real-world settings.
Bonus Reflection Prompt
“What’s one assumption you’ve made in a past project that turned into a risk — and how could this new process have helped you catch it earlier?”
Take 2 minutes to write it down — that’s where growth begins.
What’s Next
Click “Mark Complete” to continue to Module 5: Rationalizing and Describing Risks Clearly
You’ve surfaced the raw ideas — now it’s time to shape them into clear, actionable risk statements that feed directly into your risk register and project strategy.
Let’s keep building.
Lesson 5.1 Overview: Cleaning Up Your Risk List
Risk identification often leaves you with a long, messy, unfiltered list — and that’s a good thing. But now it’s time to turn that list into a practical, focused tool your team can use to drive action.
In this lesson, you’ll learn how to:
Merge duplicate or redundant risks
Remove non-risks and irrelevant issues
Escalate out-of-scope risks
Assign clear, trackable identifiers
Prepare your risk register for execution and monitoring
This is where your raw data becomes a decision-making asset.
Step 1: Merge Duplicate Risks
Duplicate risks are common — especially in large teams or multiple brainstorming groups.
Example:
“Supplier delay”
“Vendor late on component X”
➡️ Combine into:
“Third-party supplier delay may impact timeline for key project deliverables.”
? Tip: Always involve your team in these decisions. Merging risks without discussion may cause contributors to disengage if they feel their input was dismissed.
Step 2: Remove Non-Risks
Not everything captured is a risk. During review, eliminate:
Current issues (already occurring)
Assumptions that are not uncertainties
Items that don’t impact project objectives
? Ask: Is this uncertain? Can it impact objectives? If no, it doesn’t belong in your risk register.
Step 3: Escalate Out-of-Scope Risks
Some risks are valid — just not within your project’s control.
Examples:
Organizational policy changes
Portfolio-level dependencies
External regulations
What to do:
Document them in your Escalation Log
Assign them to the appropriate governance body or sponsor
Track who received them and note any follow-up required
This ensures visibility while keeping your core register focused on what your team can act on.
Step 4: Assign Unique Risk IDs
Clarity matters when managing a growing risk list.
Best practice:
Use simple sequential codes: RISK-001, RISK-002, etc.
Or group by category: TECH-01, SCHED-03, EXTRNL-02
Unique IDs help you:
Reference risks in reports or meetings
Avoid confusion with similarly worded risks
Track lifecycle from identification to closure
? Use our Risk ID Generator Template for easy setup.
Reflect & Apply
Take a moment to consider:
What risk on your last project could’ve been removed or merged earlier with this method?
What escalation-worthy risks do you often hold onto too long?
? Share your thoughts in the course comments or use the reflection worksheet. This is where your facilitation practice gets sharper.
What’s Next
Click “Mark Complete” to continue to Lesson 5.2: Describing Risks Clearly
Now that your list is cleaned up, we’ll focus on writing clear, effective risk descriptions that guide ownership and action.
You’re turning ideas into strategy — keep going!
Lesson 5.2 Overview: Writing Clear, Actionable Risk Statements
You’ve identified a ton of risks. Great start. But now it’s time to make those risks usable.
If you can’t describe a risk clearly, you can’t assess, assign, or manage it.
That’s where risk meta language comes in. This structured format makes your risks easier to:
Understand across all stakeholders
Assess for impact and probability
Take action on with confidence
What is Risk Meta Language?
It’s a structured sentence format for writing risk statements clearly and consistently.
The format:
As a result of [cause], [risk event] may occur, which could [impact or effect].
This format ensures every risk:
Has a trigger (cause)
States the uncertainty (risk event)
Shows the consequence (effect on objectives)
Opportunity Example (Don’t Forget These!)
Opportunities are positive risks — and they deserve the same clarity.
Example:
As a result of early completion of development, we may be able to launch ahead of schedule, which could increase market share.
Add these to your risk register with the same meta structure.
Bonus Tip: Map Risks to Project Objectives
Great risk statements are just the beginning. Make them even more valuable by mapping each risk to your key project objectives.
Why?
It helps prioritize risks based on impact
It clarifies reporting for stakeholders
It shows which deliverables carry the most uncertainty
Use your Risk Breakdown Structure (RBS) or the included mapping table to group risks by objective — e.g., “On-time Delivery” might include:
Supplier delay
Regulatory bottleneck
Governance review lag
This is real-world risk management, not just theory.
Reflect & Apply
Pick one vague risk from your last project or workshop and rewrite it using the meta language format.
– Share it in the comments — or use the Risk Statement Builder to draft new ones for your current project.
Up Next: Documenting & Managing the Register
Click “Mark Complete” to continue to Lesson 5.3: Module 5 Conclusion
We’ll learn how to track, maintain, and communicate your risk list so it doesn’t just sit in a spreadsheet — it drives results.
Keep going. You’re doing excellent work!
Lesson Complete: You Mastered Risk Rationalization & Description
Congratulations — you’ve wrapped up Module 5!
What started as a messy brainstorm is now a refined, structured, and ready-to-use risk list.
And that’s what real risk professionals do.
You’ve just practiced the core techniques that turn a spreadsheet into a strategic tool your entire team can rely on.
What You Learned
Let’s lock in the key takeaways from this module:
A clean risk register is a powerful tool
You don’t need more risks — you need better ones. Clear, specific, and relevant.
Every risk should be:
Assigned a unique ID
Clearly stated using cause-risk-effect meta language
Mapped to key objectives so you can prioritize and report effectively
Keep it actionable
Merge duplicates to eliminate redundancy
Remove non-risks and issues that don’t belong
Escalate out-of-scope risks to the right team, PMO, or sponsor
Don’t forget opportunities
Positive risks = competitive advantage when captured and managed proactively.
Your Action Steps
Take a moment before moving on to the next module.
Do this now:
What’s one improvement you’ll make to your next risk register?
Open an old risk list — try rewriting one vague risk using the cause-risk-effect format.
? Share it in the course community — your “before and after” might help someone else level up, too.
Coming Up Next: Building the Risk Register
Now that your register is clean and actionable, what’s next?
We’re going to cover:
How to document and store your register
How to keep it updated over time
How to communicate it effectively across your team and stakeholders
This is where risk management becomes a continuous habit, not a one-time event.
Let’s keep building. You’re doing excellent work — I’ll see you in the next module.
Lesson: Build Your Risk Register
Welcome to this module — where we turn your cleaned-up risk list into your most powerful project risk tool:
✅ The Risk Register.
You’ve captured risks. You’ve refined them.
Now it’s time to document them in a way your team can track, manage, and communicate from kickoff through delivery.
What Is a Risk Register?
A risk register is more than a list — it’s a living, evolving document that helps you:
Track risks across the lifecycle
Communicate with stakeholders
Assign and follow up with risk owners
Support compliance and audit reviews
Drive action through clear visibility
It’s used by you, your team, executives, sponsors, and even auditors.
Formatting Best Practices
Your risk register should be easy to use, easy to read, and always up to date.
Here’s how to make it usable:
Use Excel or Google Sheets (or a risk app like RAIDLOG.com — link provided below)
Freeze column headers and apply filters for ease of navigation
Use color codes (Red = High, Yellow = Medium, Green = Low)
Keep your formatting clean and minimalist — highlight what matters
Update it regularly: at each project meeting, milestone, or checkpoint
? Pro tip: A risk register that collects dust isn’t risk management — it’s a liability.
Self-Check
Before we move on, ask yourself:
Is your current register clear and complete?
Does it track ownership, status, and actions?
Are there fields you’re missing that could improve usability?
Is it being used daily, or just once and forgotten?
Coming Up Next: Assigning Risk Owners
Now that your register is in place, it’s time to assign the right people to manage the risks.
We’ll cover how to:
Choose risk owners effectively
Communicate roles and responsibilities
Keep accountability alive throughout execution
You’re building a real, functional risk process. Keep going — I’ll see you in the next lesson.
Lesson: Assigning Risk Owners
Welcome back.
Assigning risk owners isn’t just a checkbox — it’s the first move in real accountability.
If no one owns the risk?
Nothing gets done.
Why Ownership Matters
Every risk needs a named owner
Ownership = responsibility to act, update, escalate, and track
Without it, risks drift… and eventually turn into issues
Remember: Risk ownership is not the same as task ownership.
Risk owners don’t have to fix the problem themselves — they make sure the problem doesn’t get ignored.
Communicate Ownership Clearly
Once you’ve selected a risk owner:
Speak directly – don’t rely on silence or meeting notes
Set expectations – clarify:
What they’re responsible for
When to report status or escalate
What support is available (budget, team, PM guidance)
Follow up in writing – confirm assignments via email, register, or action tracker
? Use the downloadable email template to confirm ownership clearly.
Document the Ownership
Add the owner’s name to the Risk Register
Update it if:
Ownership shifts due to role changes
The risk evolves
New mitigation actions are required
Make it a habit:
Review ownership during every risk review
Track updates by owner for full traceability
Accountability is not a one-time act. It’s a system you maintain throughout the project.
Self-Check
Ask yourself:
Does every risk have a named owner?
Have those owners been directly notified and briefed?
Are expectations clear — and documented?
Do you revisit ownership at every review?
If you answered “yes” to all four, you’re not just assigning owners — you’re building a culture of accountability.
Coming Up Next: Module Conclusion
With ownership in place, your next job is to keep the risk register alive.
We’ll walk through:
Review cadence
Update strategies
Status tracking
Stakeholder communication
You’re doing the hard stuff now — the stuff that separates reactive PMs from proactive risk leaders.
Let’s keep building. See you in the next lesson.
Lesson: Maintaining the Register & Sustaining Risk Ownership
Congratulations — you’ve now built and assigned a complete, usable risk register.
More importantly? You’ve learned that real risk management doesn’t end after the workshop.
This is where it starts to matter.
Key Takeaways
1. Keep It Clear, Complete, Current
Your register is a living tool.
Clear = Every risk is well described
Complete = No missing owners or categories
Current = It gets updated as risks evolve
A stale register = silent failure
A current register = proactive leadership
2. Ownership Is the Heartbeat
Assigning owners isn’t optional — it’s essential.
Each risk has a named and empowered owner
Owners know what to do and how to escalate
Updates and follow-through keep risks from slipping through the cracks
Remember: Ownership means accountability, not overwork.
3. Review and Communicate Often
Even great registers fail when they go unused.
Best practices:
Schedule risk review meetings tied to project milestones or cadence (e.g. biweekly)
Use updates to trigger discussions, not just status
Keep all stakeholders informed — no surprises when risks emerge
Risk management is a conversation — not just a spreadsheet.
Self-Check
Ask yourself these 3 questions:
Is every risk assigned to the right owner?
Are owners clear on expectations and equipped to act?
Do we review and update the risk register regularly as the project changes?
If you answered “yes” to all three — you’re well ahead of most project teams.
What’s Coming Up Next
You’ve built the engine. Now it’s time to keep it running.
In the next module, we’ll focus on:
Communicating your risks to the right people
Updating the register as risks evolve
Sustaining the process throughout the full project lifecycle
Risk leadership doesn’t end at planning.
Let’s keep momentum going — I’ll see you in the next module.
Lesson: Post-Workshop Communication
You ran the risk workshop — great.
But here’s the truth: most of the value happens after the session ends.
Just like in the military:
“No plan survives first contact with the enemy.”
And no risk register survives first contact with your first real risk.
The goal now?
Keep risks visible, owned, and evolving. That’s where your follow-up matters most.
Key Takeaways
1. Send a Summary Email
This isn’t just meeting minutes — this is your action blueprint.
Include:
Workshop purpose + attendees
Top threats and opportunities
Owners and assigned actions
Timeline for next review/follow-up
Use the sample template provided below to streamline this.
This email sets the tone for ownership, follow-through, and trust.
2. Share the Risk Register (The Smart Way)
Don’t just attach a spreadsheet and walk away.
Choose a sharing method that supports collaboration and version control.
Options:
Excel/Google Sheet = Easy but risky for version control
Shared Drive = Centralized but limited access control
PM Software (e.g., ClickUp, Smartsheet) = Best for permissions and tracking
Whatever you use:
Assign edit/view access intentionally
Highlight the training or documentation needed to use the register effectively
Implement version control from day one
3. Define the Next Steps
Your goal is to build momentum, not confusion.
Be clear on:
Who owns what
When it’s due
When the next review is scheduled
Who is monitoring and reporting each risk
Facilitator Pro Tip:
Have each risk owner acknowledge ownership via email or shared comment.
This builds buy-in and avoids the “I didn’t know I owned that” trap.
Self-Check
Before wrapping up, ask yourself:
Did I send a summary email that sets clear expectations?
Is my risk register shared and secure with version control in place?
Have risk owners accepted their roles and know what’s next?
If yes, then your workshop didn’t just end — it launched your risk process into motion.
What’s Coming Up Next
In the next lesson, we’ll dig into:
Updating the register as risks evolve
Maintaining accuracy and relevance
Communicating risk insights to the project team and stakeholders
The workshop is only the beginning.
Let’s make risk management a living, breathing part of your project — not a dusty artifact.
I’ll see you in the next lesson.
Lesson: Updating and Maintaining the Risk Register
Welcome back!
By now, you’ve built your risk register and assigned ownership.
But here’s the truth:
Risk management is not “set it and forget it.”
This module is all about keeping your risk register current, useful, and alive.
Key Takeaways
1. Treat the Risk Register as a Living Document
Your register should evolve with the project.
Keep it active by:
Adding new risks as soon as they’re identified
Updating statuses, owners, and actions after every major change or review
Marking risks as closed or escalated as appropriate
Don’t wait. Don’t backlog updates. A stale register creates blind spots.
2. Integrate Risk Into Everyday Work
Make risk reviews part of your project rhythm:
Include risk updates in every regular meeting — team stand-ups, sponsor briefings, steering committee check-ins
Align risk with other controls — budget reviews should include top cost risks; schedule meetings should reference timing risks
Assign a register owner (PM, RM, or designated lead) to manage consistency
Risk management becomes sustainable when it’s routine.
3. Schedule Ongoing Reviews
Use recurring calendar invites to:
Keep risk top of mind
Drive accountability
Reinforce structure in your project rhythm
Use these reviews to:
Reassess probability and impact
Update or reassign risk owners
Close, escalate, or revise risks
Track action progress
Frequency Guidelines:
High-risk projects → Weekly or biweekly
Most typical projects → Monthly
Complex or milestone-driven efforts → Reviews tied to phases or major changes
Pro Tip: Phase-based mini risk workshops work great for large programs.
Self-Check
Ask yourself before wrapping up:
Is your risk register actively maintained and never outdated?
Are regular reviews scheduled — and happening?
Do risk discussions appear in team and sponsor meetings?
Are risk owners accountable and responsive when updates are needed?
If yes — you’re operating like a real risk leader.
What’s Coming Up Next
The final module is almost here.
Next, we’ll:
Consolidate everything you’ve learned
Reflect on your progress
Celebrate the completion of this course
You’ve almost made it to the finish line.
Let’s close strong and wrap up your journey to becoming a confident risk workshop facilitator.
See you in the final module.
Lesson: Module 7 Conclusion – Sustaining Risk Management After the Workshop
Congratulations — you’ve completed Module 7!
By now, you know that the real power of risk workshops happens after they end.
This is where follow-up turns facilitation into leadership.
Key Takeaways
1. The Summary Email Is Your Bridge
Don’t just run a great workshop. Follow it up with:
A clear, concise summary email outlining:
Who attended
Key risks identified
Assigned owners
Timeline for next steps
Attach the risk register and relevant files
This email becomes your anchor of accountability and clarity.
2. Ownership Makes Risk Real
The risk register means nothing without follow-through.
Confirm risk owners in writing
Clarify responsibilities and response plans
Keep ownership updated when context or team structure shifts
Risk without an owner = risk that falls through the cracks.
3. Regular Updates Keep Risks Actionable
Don’t let the register gather dust.
Build risk reviews into your project calendar
Update risks after key milestones or incidents
Ensure status, action, and ownership fields stay current
A living risk register = fewer surprises + higher stakeholder trust.
Self-Check
Reflect on your own projects. Ask yourself:
Am I documenting and sharing workshop results every time?
Is my risk register always up to date — especially owner assignments?
Do I have scheduled risk reviews on the calendar?
If you answered “no” to any — this is your chance to tighten up your process.
Reflection & Action
Here’s your challenge:
What’s one change you’ll make to your post-workshop process?
Who do you need to loop in or communicate with to keep risks visible and managed?
Want to boost your own accountability?
? Share your plan or commitment in the course community or with your team.
Coming Up Next
In the final module, we’ll:
Tie all the pieces together
Share tools for continuous improvement
Help you step fully into your role as a go-to risk leader in your organization
You’re almost there. Let’s finish strong — I’ll see you in the final module.
Overview
You’ve already mastered the fundamentals.
Now it’s time to level up.
This lesson dives into real-world challenges, showing you how to:
Maximize team engagement (especially in remote settings)
Manage difficult personalities
Avoid common workshop traps
Sustain momentum long after the workshop ends
Key Concepts
1. Maximize Engagement (Virtual & In-Person)
Risk workshops shouldn’t be snoozefests.
In virtual settings:
Use polls, whiteboards, breakout rooms
Rotate scribes and facilitators
Live-edit your register on screen
Use icebreakers or short stories to warm up
In-person?
Bring in sticky notes, color codes, team huddles — keep it interactive, not passive.
3. Avoid the “Risk Laundry List”
Too many risks, not enough action? You’ve fallen into the laundry trap.
Avoid it by:
Prioritizing using impact & probability
Ranking risks against project objectives
Ending the session with the Top 5–10 risks and clear next steps
Use voting, scoring, or a heat map to focus and act.
4. Keep Momentum Going
Risk workshops are not one-and-done.
Schedule recurring risk reviews — don’t wait for “natural” updates
Add “new risk spotting” to weekly project meetings
Celebrate wins — give credit when risks are closed or opportunities realized
Recognize contributors in meetings or via email shout-outs
This builds buy-in and transforms your whole team into risk spotters.
Checklist
Use this quick checklist to assess your facilitation toolkit:
Do you have clear engagement strategies for virtual and in-person settings?
Do you know how to handle different participant personalities?
Are you avoiding risk overload by focusing on the most critical few?
Do you have a system for keeping momentum after the workshop ends?
Reflection & Action
What’s your biggest challenge in a risk workshop?
Which advanced tip will you apply in your next session?
What pitfalls have you hit before — and how will you avoid them next time?
Jot down your responses, or better — share them in the course community.
Coming Up
In our final module, we’ll consolidate everything you’ve learned,
equip you with a master toolkit,
and help you take the final step toward becoming a true risk workshop leader.
Let’s close strong — see you in the final module.
Overview
You’ve now crossed into the expert zone.
Module 8 was all about professional-level leadership in the risk workshop room.
This isn’t about just “running a meeting.”
You’re now:
Engaging the whole team — not just the loudest voices
Navigating tough personalities with confidence
Building momentum that lasts well after the workshop
And driving a culture of proactive risk thinking
That’s real leadership.
Key Concepts
Go Beyond the Basics
Facilitators don’t just fill in templates. They lead.
You now know how to:
Pull out insight from quiet team members
Steer dominant voices without shutting them down
Keep brainstorming focused and productive
Turn each challenge into a chance to lead and build trust
Principles to Lead By
These are your guiding ideas now:
Celebrate Wins: Publicly recognize when risks are managed or opportunities are realized.
Focus on Quality Over Quantity: A shorter, better risk list always beats a cluttered, overwhelming one.
Turn Conflict Into Strength: Even difficult personalities can become allies with the right engagement.
Inclusive = Effective: The more diverse voices you engage, the more complete your risk picture becomes.
Reflection & Action
Which of these advanced principles do you want to focus on for your next risk workshop?
What’s one thing you’ll do differently based on what you’ve learned in Module 8?
Share your answers in the course community to inspire others and spark a discussion.
Coming Up Next
You’ve mastered the core, you’ve nailed the advanced — now it’s time to pull it all together.
In our final module, we’ll:
Build your personal action plan
Give you strategies for long-term risk leadership
And celebrate everything you’ve accomplished
You’re on your way to becoming your team’s go-to risk workshop leader.
Let’s finish strong.
Overview
Congratulations — you made it.
You didn’t just watch a course.
You built real, practical skills that will change the way you lead risk conversations and strengthen your project outcomes.
From planning to post-workshop accountability, you’re now equipped to run risk workshops that matter — the kind that create clarity, drive decisions, and build proactive project cultures.
Core Takeaways from This Course
Preparation Is Everything
The best workshops start strong. That means:
Clear objectives
The right people in the room
Strong, relevant inputs (like assumptions, historical data, and key documents)
Facilitation Drives Engagement
You learned to:
Set the tone with a structured agenda and ground rules
Use brainstorming prompts like the Risk Breakdown Structure and assumption checks
Make participation easy and inclusive — especially for quiet or skeptical voices
Quality Risks Lead to Quality Action
Use the Cause–Risk–Effect format to write crystal-clear risk statements
Assign the right owners — based on authority, expertise, and willingness
Make ownership visible and supported with written communication
Keep the Register Alive
This is where most teams fail. Not you.
You’ll:
Embed regular reviews
Update after major milestones
Communicate risks as part of your daily project language
Celebrate wins and show that risk management is working
Culture is the Endgame
True risk leadership is about more than one meeting.
Reinforce the process
Lead by example
Turn these tools into team habits
Final Self-Check
Have I committed to one improvement I’ll make in my next workshop?
Which tool/template will I try first?
Have I shared my commitment publicly or with my team?
Reflection & Commitment
Take 2 minutes right now:
What’s one action you’ll take as a result of this course?
Write it down. Better yet — share it with your team or inside the course community. Public accountability boosts follow-through.
Keep Growing
Your journey as a risk leader doesn’t stop here.
Here’s how to go further:
Join the Community
Connect with other facilitators for tips, feedback, and support
Sign Up for Advanced Training
Explore deeper strategy courses at 44PM Training Academy and PMI’s learning hub
Mentor & Multiply
Bring this knowledge into your organization
Teach others. Lead the culture. Build the team you always wanted to work with
Final Word
Thank you for investing in yourself and your team.
Your next risk workshop won’t just be a checkbox.
It’ll be a turning point in how your team sees risk — and in how they see you as a leader.
Go run those workshops with confidence.
And I’ll see you in the next course.
Check out upcoming courses/events: https://44riskpm.com/events/
Set up a discovery call: https://tidycal.com/44riskpm/rmp-discovery
Connect with me on:
Business: Forty-Four Risk PM, LLC
Linkedin (Personal): Russell Parker
Website: https://44RiskPM.com
Youtube: @44RiskPM
Learn how to run risk workshops that actually work — not just meetings that get forgotten.
In this hands-on course, you'll discover exactly how to plan, facilitate, and follow up on risk workshops that drive real results. Whether you're a project manager, risk professional, or team leader, you'll walk away with practical tools, templates, and confidence to lead your own workshop — from kickoff to closeout.
We’ll cover everything you need to know:
How to prep your team and structure your session
What techniques actually help identify real risks
How to guide discussions, prioritize risks, and assign owners
How to keep your risk register relevant and your team engaged
Common pitfalls to avoid (and how to handle difficult participants)
Plus: Email templates, risk prompts, and sample workshop agendas
By the end of this course, you’ll be able to lead risk workshops that produce clear, actionable results — and support your projects from start to finish.
What You’ll Learn
Facilitate risk workshops that get real engagement
Use brainstorming, RBS, and prompts to identify risks
Prioritize risks based on impact and probability
Assign and communicate risk ownership with clarity
Maintain and update your risk register throughout the project
Build a culture of proactive risk awareness on your team
Who This Course is For
Project Managers and Risk Managers
PMP or PMI-RMP Candidates
Agile and Traditional Team Leaders
Anyone who runs or supports project risk meetings