
Investment Decision
Investment Decision-Making Process
Capital investment projects involve the outlay of large sums of money in the expectation of benefits that may take several years to accrue.
The decision whether to proceed with a capital investment project is normally made by a capital expenditure committee overseeing a process that includes the following phases:
Idea creation: Proposals can be stimulated by a regular review of the company’s competitive environment and can be encouraged by incentive schemes.
Screening: To screen out unsuitable proposals by looking at the impact of the project on stakeholders and whether they support the organisation’s strategy.
Financial analysis: A detailed appraisal of the project’s risk and return, how it will be financed, any alternatives to it and the implications of not accepting the project.
Review: A post-completion review (or audit) aims to learn from mistakes that have arisen in the project appraisal process.
Relevant Cash flows
Most financial analysis techniques that are used for analysing projects are based on the use of relevant cash flows.
Relevant cash flow: A future incremental cash flow caused by a decision (e.g. to invest in a project).
Relevant cash flows:
Future (ignore past costs)
Incremental (A cost that would have been paid anyway can be ignored)
Cash-based (Accounting items like depreciation ignore as they are not cash)
Opportunity cost: A cost incurred from diverting existing resources from their best use
Non-Relevant Costs
Questions will expect you to be able to identify costs that are not relevant to decision-making.
Non-cash flows: Depreciation and apportioned overheads (i.e. overheads that are not directly attributable to a project) are not cash flows.
Sunk and committed costs: A cost incurred in the past (i.e. sunk), or committed to, will not change whether a project goes ahead or not and is therefore not a relevant cash flow (market research is often an example of this).
Historic cost of materials: If materials that are used by a project need to be replaced, the relevant cost of the materials is the replacement cost of the material - not the price originally paid to acquire the material (i.e. the historic cost).
If such materials do not need to be replaced, the relevant cost is zero (unless there is an opportunity cost from lost revenue if the material could have been sold as scrap).The historic cost of materials should only be treated as ‘relevant’ if no indication of scrap values or replacement costs are given in a question.
Cost of labour: If labour used by a project is: Idle, then the relevant cost of using that labour is zero
At full capacity, then the cost is wages paid + contribution lost on the work that they have had to stop doing.
Finance costs: Any finance costs (e.g. dividend payments, interest payments) should not be considered as a cash flow because they are included in the cost of capital used to discount a project.
Example:
Brenda and Eddie are considering expanding their restaurant business through an investment in a new restaurant, the Parkway Diner. Brenda and Eddie have analyzed the profit made in the first year and are concerned that the project could be loss making. Their Year 1 costs and revenues are forecast as follows:
Year 1 $
Revenue 200,000
Depreciation 25,000
Materials (note 1) 49,000
Labour (note 2) 100,000
Overheads (note 3) 100,000
Profit/(loss) (74,000)
Notes:
The materials include $10,000 of surplus inventory that Brenda and Eddie have in their existing restaurants. This inventory has a scrap value of $1,000.
Labor includes 20% of the $50,000 salary of a manager of an existing branch, who will assist the existing manager of the restaurant in its first year of operation.
This is an allocation of corporate overheads.
Required:
Assess the relevant cash flows of the project in the first year to Brenda and Eddie and advise
Brenda and Eddie whether they are right to be concerned.
Solution:
Relevant Cash Flows:
Year 1 $
Revenue 200,000
Depreciation 0
Materials (49,000 – 10,000 not relevant + 1,000 scrap value) 40,000
Labor (100,000 – 10,000 not relevant) 90,000
Overheads (not a cash flow) 0
Cash flow 70,000
This is less concerning than the losses figure of $74,000 that we started with but requires further analysis to see if the project is worth pursuing (e.g. analysis of later time periods).
Payback Method
This method focuses on liquidity rather than the profitability of a product. It is good for screening and for fast moving environments.
The payback period is the length of time that it takes for a project to recoup its initial cost out of the cash receipts that it generates.
This period is sometimes referred to as “the time that it takes for an investment to pay for itself.”
The basic premise of the payback method is that the more quickly the cost of an investment can be recovered, the more desirable is the investment.
The payback period is expressed in years. When the net annual cash inflow is the same every year, the following formula can be used to calculate the payback period.
Formula / Equation:
Payback Period = Investment Required / Net Annual Cash Inflow*
*If new equipment is replacing old equipment, this becomes incremental net annual cash inflow.
It simply measures how long it takes the project to recover the initial cost. Obviously, the quicker the better.
Decision rule:
Only select projects that pay back within the specified time period
Choose between options on the basis of the fastest payback
Example:
Constant cashflow scenario
Initial cost $3.6 million
Cash in annually $700,000
What is the payback period?
Solution:
3,600,000 / 700,000 = 5.1429
Take the decimal (0.1429) and multiply it by 12 to get the months - in this case 1.7 months
So, the answer is 5 years and 1.7 months
So How Useful is This Method?
The payback method is not a true measure of the profitability of an investment. Rather, it simply tells the manager how many years will be required to recover the original investment.
Whole Life of Project?
Unfortunately, a shorter payback period does not always mean that one investment is more desirable than another.
For example, it doesn’t look at the whole life of the project
Time Value of Money
Another criticism of payback method is that it does not consider the time value of money. A cash inflow to be received several years in the future is weighed equally with a cash inflow to be received right now.
Screening
On the other hand, under certain conditions the payback method can be very useful. It can help identify which investment proposals are in the “ballpark.”
That is, it can be used as a screening tool to help answer the question, “Should I consider this proposal further?” If a proposal does not provide a payback within some specified period, then there may be no need to consider it further.
Cash Poor Companies
When a firm is cash poor, a project with a short payback period but a low rate of return might be preferred over another project with a high rate of return but a long payback period.
The reason is that the company may simply need a faster return of its cash investment.
Quick Changing Environments
And finally, the payback method is sometimes used in industries were products become obsolete very rapidly - such as consumer electronics.
Since products may last only a year or two, the payback period on investments must be very short.
Irregular Cashflows
When the cash flows associated with an investment project change from year to year, the simple payback formula that we outlined earlier cannot be used.
To understand this point. consider the following data:
Cumulative
Capital out 800 -800
Capital in 100 -700
Capital in 240 -460
Capital in 200 -260
Capital in 250 -10
Capital in 120 110
When the cumulative cashflow becomes positive then this is when the initial payment has been repaid and so is the payback period
So, in the final year we need to make 10 more to recoup the initial 800. So, that’s 10 out of 120. 10/120 x 12 (number of months) = 1.
So, the answer is 4 years 1 month.
Extension of Payback Method:
The payback period is calculated by dividing the investment in a project by the net annual cash constant inflows that the project will generate.
If equipment is replacing old equipment, then any scrap value to be received on disposal of the old equipment should be deducted from the cost of the new equipment, and only the incremental investment should be used in payback computation.
Advantages include:
It is simple
It is useful in certain situations:
rapidly changing technology
improving investment conditions
It favours quick return:
helps company growth
minimises risk
maximises liquidity
It uses cash flows, not accounting profit
Disadvantages
It ignores the timing of cash flows within the payback period (e.g. ignores that a project is more uncertain if most of the cash is received at the end of the payback period).
It ignores the cash flows after the end of the payback period and therefore the total project return.
It ignores the time value of money (a concept incorporated into more sophisticated appraisal methods). This means that it does not take into account that the value of money is lower the further into the future that the money is received.
The choice of any cut-off payback period by an organisation is arbitrary.
It may lead to excessive investment in short-term projects.
Because of these drawbacks, a project should not be evaluated using payback alone.
Return on Capital Employed (ROCE)
Return on capital employed (ROCE) is also called accounting rate of return (ARR). ROCE is another simple, traditional, approach to evaluating investments.
ROCE compares the profit from an investment project to the amount invested in the project, expressing the result as a percentage.
Profit is calculated after depreciation which we have seen is not a relevant cash flow, this failure to distinguish between relevant and non-relevant cash flows is one of the many drawbacks of this technique.
ROCE = Average annual profit ÷ Initial investment
Or
ROCE = Average annual profit ÷ Average investment
Where average investment = (Initial outlay + scrap value) ÷ 2
Initial capital cost
The initial capital cost could comprise any or all of the following:
Cost of new assets bought
Net book value (NBV) of existing assets to be used in the project
Investment in working capital
Capitalised R&D expenditure (ensure this is amortised against profit)
Decision rule:
If the expected ROCE for the investment is greater than the target or hurdle rate (as decided by management) then the project should be accepted.
Benefits of Using ROCE/ARR
Simplicity and Speed: The ROCE method is quick and straightforward, using the familiar concept of percentage returns.
Comprehensive Timeframe: Unlike the payback period, ROCE considers the entire lifespan of a project.
Comparative Analysis: As a percentage measure, ROCE allows for easy comparison of different investment options, regardless of their sizes.
General Problems with ROCE/ARR
No account is taken of timing of cash flows
It varies depending on accounting policies
It may ignore working capital
It does not measure absolute gain
There is no definitive investment signal
Key Problem with Payback and ROCE
Both payback period and ROCE ignore the time value of money.
This oversight is significant and is addressed in more advanced investment appraisal techniques discussed later in the chapter.
Time Value of Money
The time value of money refers to the principle that receiving money in the future is worth less than having the same amount today.
Example: Receiving $100 today is more valuable than receiving $100 in the future due to potential earning capacity over time.
Compounding & Discounting
Compounding
A sum invested today will earn interest. Compounding calculates the future or terminal value of a given sum invested today for a number of years. To compound a sum, the figure is increased by the amount of interest it would earn over the period. To speed up the process, we can use a formula to calculate the future value of a sum invested now. The formula is:
Example:
Suppose that a business has $100 to invest and wants to earn a return of 10%.
What is the future value at the end of each year using compound interest?
Solution:
Year 1 - 100 x 1.10 = $110
Year 2 - 110 x 1.10 = $121 or 100 x (1.10) ^ 2
Year 3 - 121 x 1.10 = $133 or 100 x (1.10) ^ 3
This future value can be calculated as:
FV = PV (1 + r) n
Where,
FV is the future value of the investment with interest
PV is the initial or ‘present’ value of the investment
r is the compound annual rate of return or rate of interest expressed as a proportion
n is the number of years
e.g., $100 x 1.1 ^3 = $133
Discounting
Discounting is compounding in reverse.
It starts with a future amount of cash and converts it into a present value.
A present value is the amount that would need to be invested now to earn the future cash flow, if the money is invested at the ‘cost of capital’.
Hence, when looking at whether we should invest in something we will be looking at future cash flows coming in. We want to know what these future cash flows are worth now, in today’s money ideally.
Discount factor = (1 + r) - n
Where r = discount/interest rate and n = time period of cash flow
PV = FV × DF
PV = FV × (1 + r)–n
Example:
A business is to receive $100 in one year’s time and the interest rate/discount rate is 10%. What is the PV of that money?
Solution:
PV = 100 /1.10 ^ 1
PV = $90.9
Discount Rate
The present value can also be calculated using a discount factor (saving all the dividing by 1.1 etc.)
The discount factor can be calculated as:
1/ (1+r) ^ n
r - rate of interest
n - number of time periods
So, the discount factor for 10% in 3 years is:
1/1.1 ^ 3 = 0.751
There are also tables that give you a list of these ‘discount factors’ – a copy of these tables is included at the end of these notes.
Hence, to calculate a present value for a future cash flow, you simply multiply the future cash flow by the appropriate discount factor.
Conventions Used in DCF
Time 0 is today, it is usual to assume that time 0 is the first day of a project, ie the start of its first year.
Time 1 is the last day of the first period (normally a year).
A cash flow which occurs during the course of a time period is assumed to occur all at once at the end of the time period (at the end of the year).
A cash flow which occurs at the start of a time period is taken to occur at the end of the previous time period e.g. a cash outlay of $5,000 at the start of time period 2 is taken to occur at the end of time period 1.
Annuities
An annuity is a constant annual cash flow for a number of years. If a project involves equal annual cash flows (or annuities) then each future cash flow can be discounted separately back to a present value, but it is quicker to use a single discount factor (called an annuity factor or a cumulative discount factor).
PV = Annual Cash flow × AF
AF = {1- (1+r) – n} ÷ r
Annuity Tables
You will be provided with an Annuity Table (sometimes referred to as a Cumulative Present Value Table), which provides pre-calculated annuity factors for various different discount rates over various periods. So again, you have a choice. For example, for a three-year annuity at 10%:
There might be a small difference due to rounding. The tables should not be used as a substitute for knowing how to use the formula. Remember, the tables only cover a small range of discount rates and time periods, and you may be required to calculate a discount factor or annuity factor for variables outside of this range.
Example:
A firm has arranged a 10-year lease at an annual rent of $17,264. Each rental payment is to be made at the start of the year.
Required:
What is the present value of the lease at 12%? (Give your answer to the nearest $.)
Solution:
$109,247
When discounting we are assuming that cash flows arise the end of the year, so the payments at
the start of years 1-10 can be viewed as a payment at time 0 and then nine payments at the end
of each fo the years 1-9. So, when we use the annuity table, we are looking at time periods 1-9.
r = 12%
n = 9 (1st payment now, 10th payment at the end of time 9)
Annuity factor = 5.328 for time periods 1-9 at 12%.
PV = 17,264 (the first payment is not discounted because it is paid in advance) + (5.328 × 17,264) = 109,247
Perpetuities
A perpetuity is an annuity that continues indefinitely into the foreseeable future, with no end date for the cash flows.
Cash Flow Analysis:
Perpetuities can be evaluated using a single discount factor.
This approach requires the use of a specific formula, which should be memorized for calculations.
PV = Cash flow ÷ r Or PV = Cash flow × (1÷ r)
1 ÷ r is known as the perpetuity factor.
The PV of a growing perpetuity is found using the formula:
PV = Cash flow at T1 × 1÷ (r – g)
1 ÷ (r – g) is known as the perpetuity factor with growth.
Example:
If a project involved the outlay of $20,000 today and provided a definite return of $3,000 per year
for the foreseeable future.
Required
Would you accept the project?
(Again, assume that you could get a return of 6% on investments of similar risk.)
Solution
The perpetuity factor here is: 1/0.06
So, the present value of the future cash flows is $3,000 × 1/0.06 =$50,000
And the present value of the inflows exceeds the cost of the project, so the project is acceptable.
Advanced and Delayed Annuities and Perpetuities
The use of annuity factors and perpetuity factors both assume that the first cash flow will be occurring in one year's time. Annuity or perpetuity factors will therefore discount the cash flows back to give the value one year before the first cash flow arose. For standard annuities and perpetuities, this gives the present (T0) value since the first cash flow started at T1.
Be careful: if this is not the case, you will need to adjust your calculation.
Advanced Annuities and Perpetuities
Some regular cash flows may start now (at T0) rather than in one year's time (T1).
Calculate the PV by ignoring the payment at T0 when considering the number of cash flows and then adding one to the annuity or perpetuity factor.
Advanced Annuities: An Illustration
A 5-year $600 annuity is starting today. Interest rates are 10%. Find the PV of the annuity.
Solution
This is essentially a standard 4-year annuity with an additional payment at T0. The PV could be calculated as follows:
PV = 600 × (1 + 3.17) = 600 × 4.17 = $2502
Advanced Perpetuities: An Illustration
A perpetuity of $2,000 is due to commence immediately. The interest rate is 9%. What is the PV?
Solution
This is essentially a standard perpetuity with an additional payment at T0. The PV could be calculated as follows:
PV =2,000 × (1 + 1÷ 0.09) = 2,000 × 12.11 = $24,222
Delayed Annuities and Perpetuities
Some regular cash flows may start later than T1.
These are dealt with by:
Applying the appropriate factor to the cash flow as normal
Discounting your answer back to T0
Delayed Annuities – An illustration
A seven-year annuity of $450 starting in five years’ time. Interest rates are 11 %. Find the present value of the cash flow.
A seven-year annuity of $450 starting in five years’ time.
Step 1: Look up the 7-year AF: AF = 4.712
Step 2: Discount the annuity as usual: 450 × 4.712 = $2,120.40
Note that this gives the value of the annuity at T4
Step 3: Discount the answer back to T0: 2,120.40 × 0.659 = $1,397.34
Delayed Perpetuities – An illustration
A perpetuity of $33,000 commencing at T2. Interest rates are 22%. Find the present value of the cash flow.
A perpetuity of $33,000 commencing at T2.
Step 1: Calculate the perpetuity factor: 1/0.22 = 4.545
Step 2: Discount the perpetuity as usual: 33,000 × 4.545 = $149,985
Note that this gives the value of the perpetuity at T1
Step 3: Calculate the PV: 149,985 × (1/1.22) = $122,939
The Net Present Value (NPV)
To appraise the overall impact of a project using DCF techniques involves discounting all the relevant cash flows associated with the project back to their PV.
If we treat outflows of the project as negative and inflows as positive, the NPV of the project is the sum of the PVs of all flows that arise as a result of doing the project.
The NPV represents the surplus funds (after funding the investment) earned on the project, therefore:
If the NPV is positive – the project is financially viable
If the NPV is zero – the project breaks even (just returning enough money to cover the funding costs)
If the NPV is negative – the project is not financially viable
If the company has two or more mutually exclusive projects under consideration it should choose the one with the highest NPV
The NPV gives the impact of the project on shareholder wealth.
Assumptions used in discounting
Unless the examiner tells you otherwise, the following assumptions are made about cash flows when calculating the net present value:
All cash flows occur at the start or end of a year
Although in practice many cash flows accrue throughout the year, for discounting purposes they are all treated as occurring at the start or end of a year. Note also that if today (T0) is 01/01/20X0, the dates 31/12/20X1 and 01/01/20X2, although technically separate days, can be treated for discounting as occurring at the same point in time, i.e. at T1
Initial investments occur at T0 other cash flows start one year after that (T1).
In project appraisal, the investment needs to be made before the cash flows can accrue. Therefore, unless the examiner specifies otherwise, it is assumed that investments occur in advance. The first cash flows associated with running the project are therefore assumed to occur one year after the project begins, i.e. at T1
Also, note you should never include interest payments as cash flows within an NPV calculation as these are taken account of by the cost of capital.
EXAMPLE: An organisation is considering a capital investment in new equipment. The estimated cash flows are as follows.
Year
Cash flow
$
0 (240,000)
1 80,000
2 120,000
3 70,000
4 40,000
5 20,000
The company’s cost of capital is 9%. Calculate the NPV of the project to assess whether it should be undertaken.
Year Cash flow DF at 9% PV
0 (240,000) 1.000 (240,000)
1 80,000 0.917 73,360
2 120,000 0.842 101,040
3 70,000 0.772 54,040
4 40,000 0.708 28,320
5 20,000 0.650 13,000
NPV
29,760
–––––––
The PV of cash inflows exceeds the PV of cash outflows by $29,760, which means that the project will earn a DCF return in excess of 9%, i.e. it will earn a surplus of $29,760 after paying the cost of financing. It should therefore be undertaken.
Present Value Tables
(1 + r)–n is called the discount factor (DF). In the exam, you will be provided with a Present Value table that gives the discount factors for various different discount rates over various time period. So, to find the DF, for example if r = 10% and n = 5, you can
Advantages of NPV
When appraising projects or investments, NPV is considered to be superior (in theory) to most other methods. This is because it:
Considers the time value of money – discounting cash flows to PV takes account of the impact of interest, inflation and risk over time. These significant issues are ignored by the basic methods of payback and annual rate of return (ARR or ROCE)
Is an absolute measure of return – the NPV of an investment represents the actual surplus raised by the project. This allows a business to plan more effectively. Neither ARR nor payback is an absolute measure.
Is based on cash flows rather than profits – the subjectivity of profits makes them less reliable than cash flows and therefore less appropriate for decision making.
Considers the whole life of the project – methods such as payback only consider the earlier cash flows associated with the project. NPV takes account of all relevant flows associated with the project. Discounting the flows takes account of the fact that later flows are less reliable, which ARR ignores.
Should lead to maximisation of shareholder wealth. If the cost of capital reflects the investors’ (i.e. Shareholders’) required return, then the NPV reflects the theoretical increase in their wealth. For a company, this is considered to be the primary objective of the business.
Disadvantages of NPV
It is difficult to explain to managers. To understand the meaning of the NPV calculated requires an understanding of discounting. The method is not as intuitive as techniques such as payback.
It requires knowledge of the cost of capital. The calculation of the cost of capital is, in practice, more complex than identifying interest rates. It involves gathering data and making a number of calculations based on that data and some estimates. The process may be deemed too protracted for the appraisal to be carried out.
It is relatively complex. For the reasons explained above, NPV may be rejected in favour of simpler techniques.
Internal Rate of Return
The IRR is essentially the discount rate where the initial cash out (the investment) is equal to the PV of the cash in.
So, it is the discount rate where the NPV = 0
It is actual return on the investment (%).
Consequently, to work out the IRR we need to do trial and error NPV calculations, using different discount rates, to try and find the discount rate where the NPV = 0.
The good news is you only need to do 2 NPV calculations and then apply this formula:
Where,
L = Lower discount rate
H = Higher discount rate
NPV L = NPV @ lower rate
NPV H = NPV @ higher rate
If the IRR is higher than the cost of capital, the project should be accepted.
Note:
IRR is greater than the required return (cost of capital)
Return from the investment is above that which is required
(undertake project)
IRR is less than the required
return (cost of capital)
Return from investment is below that which is required
(don’t undertake project)
IRR is equal to the required return
(cost of capital)
Return from investment is the same as cost of
Example:
A project has a positive NPV of $15,000 when discounted at 6% and a negative NPV of $3,000 when discounted at 12%.
Required:
Calculate the internal rate of return.
Solution:
11%
IRR = 6 + (15/(15 + 3) × 6) = 11%
Little Tricks
If all the cashflows are the same
This is an annuity - simply take the Initial Cost / annual inflow - this gives you the cumulative discount factor (annuity factor).
Then go to the annuity table and look for this figure (in the row for the number of years the project is for) - the column in which the figure is found is the IRR!
If the cashflows are the same and go on forever.
This is a perpetuity - simply take the Annual inflow / Initial cost and turn it into a percentage. That’s the IRR! Done.
Advantages of IRR
Considers the time value of money
Easily understood percentage
Uses cash do not profit
Considers whole life of project
Increases shareholders’ wealth
Disadvantages of IRR
Does not produce an absolute figure (percentage only)
Interpolation of the formula means it is only an estimate
Fairly complicated to calculate
Non-conventional cashflows can produce multiple IRRs
Interpreting the IRR
The IRR provides a decision rule for investment appraisal, but also provides information about the riskiness of a project – i.e., the sensitivity of its returns.
The project will only continue to have a positive NPV whilst the firm’s cost of capital is lower than the IRR.
A project with a positive NPV at 14% but an IRR of 15% for example, is clearly sensitive to:
- an increase in the cost of finance
- an increase in investors’ perception of the potential risks
- any alteration to the estimates used in the NPV appraisal.
IRR of a perpetuity
To calculate the IRR of a perpetuity:
IRR is the discount rate where NPV = 0.
Perpetuity formula: PV=Annual Inflow / r
At NPV = 0:
Initial Investment = Annual Inflow / r
Rearrange to find IRR:
r = Annual Inflow / Initial Investment
Example: For an initial investment of $30,000 and an annual inflow of $4,000:
r = 4,000 / 30,000 = 13.33%
Computer based exam method
In a computer-based exam you can use the =IRR function to calculate the project’s IRR. Note. The undiscounted cash flows are used for the IRR calculation. Also, the spreadsheet IRR formula does not work if the cash flows are set up as annuities.
NPV v IRR
The net present value (NPV) method has several important advantages over the internal rate of return (IRR) method.
NPV is often simpler to use. As mentioned earlier, IRR may require hunting for the discount rate that results in a net present value of zero.
This can be a very laborious trial-and-error process, although it can be automated to some degree using a computer spreadsheet.
A key assumption made by IRR is questionable. Both methods assume that cash flows generated by a project during its useful life are immediately reinvested elsewhere.
However, the two methods make different assumptions concerning the rate of return that is earned on those cash flow.
NPV assumes the rate of return is the discount rate
IRR assumes the rate of return is the internal rate of return on the project.
So, if the IRR is high, this assumption may not be realistic. It is more realistic to assume that cash can be reinvested at the discount rate - particularly if the discount rate is the company’s cost of capital. For example, by paying off the company’s creditors
In short, when NPV and IRR do not agree, it is best to go with NPV. Of the two methods, it makes the more realistic assumption about the rate of return that can be earned on cash flows from the project.
Absolute V Percentage Figure
IRR has several weaknesses as a method of appraising capital investments. Since it is a relative measurement of investment worth, it does not measure the absolute increase in company value (and therefore shareholder wealth), which can be found using the net present value (NPV) method.
Mutually Exclusive Projects
There is a potential conflict between IRR and NPV in the evaluation of mutually exclusive projects, where the two methods can offer conflicting advice as which of two projects is preferable.
For example, a small project may have a higher IRR but a lower NPV than a very big project.
Where there is conflict, NPV always offers the correct investment advice.
Assessment of DCF Methods of Appraisal
Discounted Cash Flow (DCF) methods of appraisal are widely used in investment analysis and project evaluation due to their numerous advantages:
Cash Flow-Based: DCF methods rely on actual cash flows rather than accounting profits, offering a more accurate representation of a project's value.
Consideration of Time Value of Money: DCF incorporates the principle that a dollar today is worth more than a dollar in the future, providing a realistic evaluation of cash flows.
Comprehensive Cash Flow Analysis: All cash inflows and outflows throughout the project's life are included, ensuring a holistic appraisal.
Flexibility in Timing of Cash Flows: DCF methods account for the exact timing of cash flows, which is critical for projects with uneven cash flow patterns.
Universally Accepted Metrics: The Net Present Value (NPV) and Internal Rate of Return (IRR) are standard measures in financial analysis, providing clarity and consistency.
Assumptions of DCF Methods
NPV Assumption: It is assumed that cash inflows are reinvested at the project’s discount rate, typically the cost of capital (e.g., 10%).
IRR Assumption: It is assumed that cash inflows are reinvested at the internal rate of return (IRR).
However, these assumptions may not hold true in real-world scenarios, introducing potential inaccuracies.
Potential Problems with DCF Methods
Forecasting Challenges: Predicting future cash flows accurately can be difficult, especially for projects with significant uncertainty.
Capital Rationing: The NPV decision rule—accepting all projects with positive NPVs—does not apply when investment capital is limited.
Estimating the Discount Rate: Determining the appropriate cost of capital can be complex and subjective, and it may vary over the project's lifetime.
Changing Cost of Capital: Economic conditions or company-specific factors might cause fluctuations in the discount rate, complicating the evaluation.
Stakeholder Conflict: The NPV method assumes the primary goal is shareholder wealth maximization, which may conflict with the interests of other stakeholders, such as employees or the community.
Conventional Cash Flows:
Definition: A single outflow (investment) followed by multiple inflows (returns).
Example: Initial investment of $10,000 (outflow) followed by yearly inflows of $2,000, $3,000, $5,000.
Cash Flow Pattern: −,+,+,+
Key Feature: Only one sign change in cash flows (negative to positive).
Non-Conventional Cash Flows:
Definition: Cash flows with more than one sign change (outflows and inflows alternate).
Example: $10,000 investment, followed by $5,000 inflow, then $3,000 maintenance cost (outflow), and $4,000 inflow.
Cash Flow Pattern: −,+,−,+
Key Feature: Multiple sign changes in cash flows.
Implications:
Conventional Flows: Easier to analyze; results in a single IRR.
Non-Conventional Flows: Can yield multiple IRRs, making analysis more complex.
Course Overview
This course has been designed to understand the Investment Appraisal Techniques and Application from scratch. I introduce the students to different methods used in appraising capital investments and then gradually we dive deep into the technical financial calculations on how to evaluate the projects that would increase the share holder wealth. We will use different methods of investment appraisal such as Payback Method, Discounted Payback, ARR, NPV and IRR.
To apply these methods in detail and with accuracy, we will learn and practice discounted cash flow method which is commonly known as DCF technique. With the help of DCF we will learn how to calculate annuities, perpetuities, NPV and IRR. To make it mor interesting and relevant to real life, we will also learn the impact of inflation and taxation in the calculation of NPV and IRR
Bonus
As the last part of this course we will learn about WACC (Weighted Average Cost of Capital) This is an important concept to understand as all of the discounting of cash flows will be done based on WACC
Who should take this course ?
This course is equally beneficial for working accountants and finance professionals as well as students who are completing their qualifications related to accounting and finance.
Accounting and Finance Professionals, Entrepreneurs, Business Owners, Startups and Accounting and Finance students doing BBA, MBA, ACCA, CIMA, CPA, CFA, CAT, ICAEW
What is included in the course ?
- Payback Period,
- ROCE (Return on Capital Employed)
- Discounted Cash Flow - DCF
- Net Present Value - NPV
- Internal Rate of Return – IRR
- Allowing for Inflation in Project Appraisal
- Allowing for Taxation in Project Appraisal
- Specific Investment Decisions
- Project Appraisal in Risk
- Certainty Equivalents and Mutually Exclusive Projects
- Probability Analysis in Project Appraisal
- Lease or Buy Decisions
- Asset Replacement Decisions
- Equivalent Annual Benefits in Mutually Exclusive Projects
About the instructor
A qualified accounting and finance professional with over twenty years of extensive experience in diversified industry sectors such as auditing, large scale manufacturing and oil and gas.
Like most accounting and finance professionals, I started my career as finance executive and then over the years rose to the position of CFO in a multinational company in oil and gas industry.
I have also worked as a consultant with the World Bank and European Union on different projects in Middle East, Eastern Europe and CIS countries during 2011 to 2018 as a principal consultant for IFRS and Financial Management.
I am qualified professional with three professional qualifications MBA, ACCA and CIMA UK. I have been teaching IFRS, Financial Reporting, Financial Management and Performance Management for over fifteen years and my focus areas are ACCA and CIMA qualifications.