Calibration, Installation & Commissioning of Instrumentation
What you'll learn
- Understand the life cycle of industrial plant from planning to maintenance
- Planning Understand that With out planning you will not be able to carry out a plant safely and in time
- Risk assessment HAZOP Hazard and operability study
- Design & Detailed engineering Design basis,
- Design document and The purpose of Instrumentation and Control (I&C)
- Codes, Standards, and Regulatory Requirements
- Control System Philosophy BPCS Basic Process Control System and SIS Safety Instrumented System
- Understand Hazardous Area classification according to ATEX and NFPA
- Understand P&ID Piping and Instrumentation Diagram how to read and How DESIGN using AUTOCAD PLANT 3D
- Know How to select your Instrument Pressure Gauge ,Switch and Transmitter
- Know How to select your Instrument temperature measuring devices
- Know how to select Level and Flow Devices
- Instrumentation documents (Instrument index , Input /Output List and Specification data sheet
- Control system preparation , Instrument Loop Diagram ILD , Cause and effect and control logic
- Installation procedures , Installation guidelines Hock up diagram
- Instrumentation pre-commissioning Confirm calibration settings , ranges
- Cold loop check and Hot Loop Check procedures
- Pre commissioning procedures like FAT factory acceptance test
- Understand what is Cold Commissioning and Hot Commissioning and Know what is the difference between them
- Understand what is Start up and operation
- Maintenance types
Requirements
- Some engineering or field knowledge is preferable but freshers are welcome.
- All the concepts are explained in depth using an easy to understand language to allow students to build their knowledge from the ground up
Description
It is so important for any Engineer deal with industry facility to understand the phases of project life cycle
Project life cycle of Process Field Instrumentation
1 Planning
2 -Design
3- Installation
4 -Pre- Commissioning
5- commissioning
6-Startup
7- Initial Operation
8 - Maintenance
Planning With out planning you will not be able to carry out a plant safely and in time
Which items you have to plane for fast , safe and successful plant execution
•Risk assessment (•Safety is the first priority during any process eg. "HAZOP" (Hazard and operability analysis ) It is to identify and assess risk)
•Completion priority
•Documents
•Manpower
•Tools
Design
•Design basis
•"P&ID" design
Installation
•Initially, Instrumentation Engineers and supervisors mark the :
1.location of Instruments.
2.Junction boxes.
3.Identify cable routing.
• Locations will be marked on nearby structures, vessels, etc.
•Civil foundations, structural, mechanical static equipment will be installed first.
•Based on the work front available to install Instruments, the Instrumentation team will start their activities.
Pre- Commissioning
Confirm calibration settings , ranges
Calibration is adjustment to ensure that the instrument give accurate reading.
Its done by comparing the readings on an instrument with reference one.
Cold and Hot loop check
Cold loop testing is done without powering up, ie the wiring integrity is tested through loop resistance and continuity check.
Hot loop test is done by simulation of the automation controller (PLC, DCS) and the I/O, Functions etc. are tested.
Stand alone tests confirm no damage after installation
• FAT Factory acceptance testing (manufactory) is simply a test for a newly manufactured control system that takes place at your factory or your workshop before you ship the control panel to the customer.
• SAT Site acceptance testing (vendor or commissioning team)
• SIT Site integration testing (confirm equipment functions as a system)
Commissioning
Usually it is the phase when design process fluids are introduced to the systems and sub system
Cold commissioning
•Dry commissioning : tests and procedures without fluids yet introduced to the plant
•Example activities : Interlock and emergency shut-down tests
•Control system sequence checks
•Wet commissioning : tests and procedures with safe fluid (water or solvent) has been introduced into the systems and sub-systems
•Example activities “running pumps with closed loops”
Hot Commissioning "Live commissioning"
•Design process fluids are introduced to the systems and sub-systems
•Example activities “running pumps with closed loops”
Startup The phase in a project where the entire plant (all systems and sub-systems) are taken into operation, Process fluids are introduced and process conditions are established with the intent of making products
Initial operation The entire plant is running in continuous operation, fine-tuned and prepared for the performance test.
Maintenance
•Preventive Maintenance
•Corrective Maintenance
•PREDICTIVE Maintenance
•EMERGENCY Maintenance
•RENOVATION Maintenance
I hope you will enjoy learning.
Who this course is for:
- This course is for: Experienced as well as Beginners in planning, construction & Commissioning of Process field instrumentation (Engineers, Technicians, Supervisor, Foreman etc.)
- Instrumentation Engineer
- Operation Engineer
- Instrumentation Technicians
- Process Engineer
Instructor
An Instrumentation and Control Engineer with over 13 years of experience in Instrumentation and Control in EDEPC, East Delta Electric Production Company, Egypt
Certified Instructor from Egyptian Engineers Syndicate and with over 200 hours of active training in instrumentation and control
· Planning organization and Supervision of versatile I&C activities.
· Troubleshooting of problems within instruments Such as:
(Valves, Pressure/Flow/Level Transmitters, Temperature/ Pressure/ Flow/ Level Switches, Speed/Temperature Sensors).